Skip to main content

Zirui tunnel is the controlling node project of Chengdu hub west loop project, and is also the last key link to realize the double-line completion between Chengdu South Station and Chengdu West Station, which will greatly improve the evacuation capacity of Chengdu railroad hub after breakthrough, and is of great significance to enhance the status of Chengdu railroad hub and achieve bus operation of the railroad circuit.

The slurry shield "ZiRui"(excavation diameter 12.84m) was used to excavate in the large grain size water-rich sand and pebble strata. With deep professional background, Herrenknecht separation plant , actively participates in important local projects to help the modern transportation development of the ancient city of thousands of years.

 

Scope of supply
  • 1 x HKS2400 Separation Plant
  • Slurry transfer system (integrated slurry transfer capacity 2400m³/h)
  • 12.84m excavation diameter double-mode shield (slurry/ EPB)

Other Performance

The project is located in the center of the city, the equipment covers a small area, and can withstand the high abrasion of large size, high strength, high water-rich sand and pebble strata, effectively prevent the sand and pebble stagnation discharge. The excellent performance and perfect service of the equipment have won the praise of the customers.